Iru Power Plant
| Iru Power Plant | |
|---|---|
Iru Power Plant | |
| Official name | Iru Elektrijaam |
| Country | Estonia |
| Location | Iru, Maardu |
| Coordinates | 59°27′10″N 24°55′39″E / 59.45278°N 24.92750°E |
| Status | Operational |
| Construction began | 1976 (unit 1) 2010 (unit 3) |
| Commission date | 1978 (unit 1) 2013 (unit 3) |
| Construction cost | €105 million (unit 3) |
| Owner | Enefit Green |
| Operator | Enefit Green |
| Thermal power station | |
| Primary fuel | Natural gas (units 1 and 2) Municipal solid waste (unit 3) |
| Secondary fuel | Fuel oil (units 1 and 2) |
| Cogeneration? | Yes |
| Power generation | |
| Units operational | 1 × 80 MW 1 × 110 MW 1 × 17 MW |
| Make and model | LMZ (units 1 and 2) TMZ (units 1 and 2) Sibtjazmaz (units 1 and 2) CNIM (unit 3) |
| Nameplate capacity | 207 MW |
| External links | |
| Commons | Related media on Commons |
Iru Power Plant is a co-generation power plant in Iru village, Maardu, Estonia. It is owned by Enefit Green, a subsidiary of Eesti Energia. The plant has a heating capacity of 698 MWt.